"Typical Villa Home Construction Schedule"


Gather paperwork and apply for permits
Scrape lot; Dig and pour footings; Lay stemwall block; Fill stemwall with dirt; Install pool shell
Install underground plumbing & electrical work; Prepare slab; Pre-treat for termites; Pour slab
Deliver and lay block walls; Form and pour tie beam; Strip tie beam forms
Install roof truss system; Apply roof sheething and sub fascia; Install tar paper and flashing
Frame interior walls; Install rough plumbing, air conditioning, electric, & low voltage work
Install impact glass windows and doors; Hot mop roof and lay roof tile; Install insulation
Install drywall and do stucco work; Begin storm protection installation (if applicable); Install interior doors and trim; Paint interior and exterior
Install cabinets; Install tile work; Install septic system/sewer lines
Form and lay drive and walkway; Install countertops; Install mirrors and closet shelving
Trim air conditioning, plumbing, electric, & low voltage work
Form and lay pool deck; Rough cleaning; Install sprinkler system, landscaping, and sod
Install appliances; Install carpet; Do final touch-up work; Get pool final; Do final cleaning
Schedule walk-thru with customer after certificate of occupancy is received
Close on home with Construction Office This is a quick overview of the Villa Homes construction process.

Please use this as a guide only.
Remember that schedules and producers may change from job to job.